Construction
Completion of a big project like the busway creates change and some disruption. We’re keen to be good neighbours while the work is in progress and to keep you updated so you know what to expect.
Work in progress
Summary of Eastern Busway road work and traffic restrictions. Check for current and upcoming road layout changes and work in your area while the Eastern Busway is built.
Where |
Activity |
What’s happening |
From |
To |
Pakūranga to Mattson Road |
||||
Pakūranga Plaza map |
Shopping Centre access |
Access from Reeves Road to Pakūranga Plaza will be closed until late February Pakūranga Plaza is accessable from Pakūranga Road, Tī Rākau Drive and Cortina Place |
Monday 10 February |
Late February |
Aylesbury Street |
Road closure |
Access from Reeves Road to Pakūranga Plaza, Aylesbury Street, will be closed at night between 10pm and 4am |
Monday 24 February |
Friday 6 March |
Pakūranga Road |
Utilities work |
Local watermain installation Friday night to Monday morning (24/7) *Reduced lanes eastbound* |
Friday 21 February |
Monday 24 February |
South Eastern Highway |
Within current work site |
Asphalt work in preparation for traffic lane switch |
Wednesday 26 February |
Thursday 27 February |
South Eastern Highway |
Citybound lanes closure |
South Eastern Highway - citybound closure overnight (Monday 24 February) for traffic lane switch (ongoing to mid-2025) |
Sunday 2 March |
Tuesday 4 March |
South Eastern Highway |
Lane layout changes |
Citybound lane layout changes |
Monday 24 February |
Mid-2025 |
William Roberts Road |
Utilities work |
Restricted parking Access closed between Pakūranga Road and William Roberts Road Lane layout changes - between Reeves Road and William Roberts Road |
January |
Ongoing |
Mattson Road to Tī Rākau bridge |
||||
Mattson Road |
Day work |
Permanent road resurfacing work (weather permitting) |
3 February |
17 March |
Mattson Rd to Roseburn Pl |
Utilities work |
Day and night work to complete utilities work (noise mats will be installed) |
16 February |
16 March |
Tiraumea Drive |
Tiraumea Drive closure - detour only via Mattson Road |
Building the permanent citybound lanes, footpath and cycleway |
19 February |
Late April |
Mattson Road/ Tī Rākau Drive and William Roberts Road intersection |
Night work |
Intersection opening between 18 and 21 February, weather dependent |
Tuesday 18 February |
Ongoing |
Fremantle Place |
Night work |
Periodic night work |
Thursday 16 January |
April |
Burswood, Huntington Park and Botany |
||||
Burswood |
Deconstruction and site establishment |
Deconstruction and removal of houses |
September 2024 |
February 2025 |
-
Rā Hihi (flyover)
A groundbreaking development is in progress in Pakūranga with the construction of a flyover that’s set to soar above Reeves Road and across Tī Rākau Drive. It’s an important part of the Eastern Busway project that will improve travel times and ease congestion in the area. Establishing this direct link between the South Eastern Highway and Pakūranga Road will help to reduce traffic along Pakūranga Road and Tī Rākau Drive, particularly during peak hours.
-
William Roberts Road
The new intersection of Mattson Road, Tī Rākau Drive and William Roberts Road is now open. Drivers, pedestrians and wheel users can enter and exit William Roberts Road from all directions. The northern end of William Roberts Road between Pakūranga Road and Reeves Road is closed permanently. That will enable the new intersection to connect Pakūranga Road to Rā Hihi (flyover). The northern end of William Roberts Road can be accessed from Ayr Road.
-
Construction Timeline - Burswood
-
Improving traffic flow in Pakūranga
Several options to improve local traffic flow are being looked into by the project team and are here:
- Trialing a free left turn from Pakūranga Road on to Tī Rākau Drive, including a zebra crossing in place of the existing signlised pedestrian crossing has been considered however this has potential safety implications and the potential for increased congestion during peak periods.
- Increasing the number of lanes from two to three on Tī Rākau Drive between Pakūranga Road and Aylesbury Street to enable more traffic in each light phase to turn left and right from Pakūranga Road on to Tī Rākau Drive.
- Continuing to enhance traffic signal operation. This includes changing the signalling of traffic lights from actuated to fixed timing to better ensure improved coordination of the traffic signals between Pakūranga Road and the South Eastern Highway.
- Adjusting our construction approach to continue to explore ways for Cortina Place to remain open as often as possible.
- Creating a right turn from William Roberts Road on to Tī Rākau Drive earlier than planned. It will combine the realignment of Mattson Road into a single intersection.
- Completing the flyover above Reeves Road ahead of schedule to ensure a long term solution for traffic congestion on Pakūranga Road is delivered as soon as possible.
The project team has already put some measures in place to help reduce congestion on the local road network. We have:
- Redesigned drainage into Pakūranga Plaza car park removing the need for lane closures on Pakūranga Road and Tī Rākau Drive
- Worked on the South Eastern Highway and Tī Rākau drive when traffic volumes were lowest during the Easter weekend, to minimise impacts on road users
- Adapted our approach to installing services on Tī Rākau Drive to ensure the road remained open in both directions while work took place. This avoided lane closures that were forecast to be in place from July this year.
- Reduced night and weekend work in residential areas by planning our work together with utility providers
- Encouraged the community to use public transport by keeping bus stops open, installing new bus stop signage and placing digital displays at the corner of Mattson Road and Tī Rākau Drive to show realtime journey times by bus, bike and car. The number of passengers using the bus stops closest to Pakūranga Plaza is now the highest it has been since before the Covid-19 outbreak in March 2020.
-
Timeline
-
Construction approach
Construction will take place in stages starting in Pakūranga between Pakūranga Town Centre and the Tī Rākau Drive Bridge and will progress towards Botany.
Above: Traffic staging on Ti Rākau Drive -
Facts to know during construction
-
Supporting MATES in Construction
The alliance is delighted to become a Premium Plus sponsor of MATES in Construction, an organisation helping to reduce the lives lost to suicide in the construction industry.
Alliance project director Matt Zame says that the five organisations of the alliance have been affected by suicide and the ripples it causes. "Suicide has a profound and lasting impact on the families, friends and colleagues of their lost loved ones. We’re keen to see change in the industry to ensure all of our people are safe and well. We’ve partnered with MATES to help achieve that change and to support our people to ask for help when they’re feeling low, as a regular part of life."
MATES is proud to be a part of the support team for the project looking after the alliance’s workers on site and in the project offices, too. We are stronger together.
