Construction


Work in progress
Completion of a big project like the busway creates change and some disruption. We’re keen to be good neighbours while the work is in progress and to keep you updated so you know what to expect.
Check below for current and upcoming road layout changes and work in your area while the Eastern Busway is built.
Where |
Activity |
What’s happening |
From |
To |
Pakūranga to Mattson Road |
||||
|
Reeves Road/ Aylesbury Street/ William Roberts Road intersection |
day and night work |
Final stage includes road closures of Reeves Road between William Roberts Road and Aylesbury Street - 18 October to End of November - Stop/go traffic between Reeves Road and William Roberts Road. - Two-way traffic between Aylesbury Street and Reeves Road (under Rā Hihi-flyover) Drainage completed. Work underway to build road and intersections including installation of traffic light signals 2 and 3 November - pavements work at night |
8 June |
Late November |
|
Brampton Court and Pakūranga Road intersection |
Night work |
Utilities installation 1 November - traffic lights will become live |
15 October |
1 November |
|
Pakūranga Road, from Rā Hihi - flyover to Tī Rākau Drive |
Day and night work |
Grouting the redundant storm water line along Pakūranga Road and installing cycleway separators |
27 October |
Late November |
|
Tī Rākau Drive from Mattson Road to Pakūranga Highway onramp |
Night work |
Final stormwater network work |
18 October |
19 November |
|
Bolina Crescent |
Day work |
Stormwater drainage work |
Early October |
Early November |
|
Pakūranga Town Centre |
Day and night work |
Ongoing minor works including traffic signs around Pakūranga Town Centre |
Late October |
Early December |
|
Tī Rākau Drive and William Roberts Road intersection |
Night work |
Construct median island and install traffic signals 10 to 12 November - final surfacing work |
1 November |
Mid-November |
Mattson Road to Tī Rākau bridge |
||||
|
Tī Rākau Drive intersections (Edgewater Drive east, Roseburn U-turn, Gossamer Drive) |
Night work |
24/7 work along Tī Rākau Drive from Friday 30 October to Sunday 1 November (weather dependent) Grouting redundant stormwater pipes, testing new streetlights, completing the intersection and median kerbs and laying asphalt |
28 October |
3 November |
|
Gossamer Drive intersection |
Night work |
Installing kerbs and median island and final surfacing |
Late-October |
Mid-November |
|
Edgewater Drive (east) intersection |
Night work |
Installing kerbs and median island and final surfacing |
Early-October |
Mid-November |
Burswood, Huntington Park and Botany |
||||
|
Huntington Drive |
day and night work |
Right turn into and out of Greenmount Drive closed while work is completed for busway and intersection with Tī Rākau Drive. |
Ongoing |
November 2026 |
|
Whakamaumahara Guys Reserve |
day and night work |
Construction on final stage of Eastern Busway |
March 2026 |
Mid 2027 |
-
Timeline

The project timeline is a summary of the main activities on the project between now and 2027. See at a glance what’s in progress and what’s coming up in the next few years.
-
Facts to know during construction

-
Supporting MATES in Construction

The alliance is delighted to become a Premium Plus sponsor of MATES in Construction, an organisation helping to reduce the lives lost to suicide in the construction industry.
Alliance project director Matt Zame says that the five organisations of the alliance have been affected by suicide and the ripples it causes. "Suicide has a profound and lasting impact on the families, friends and colleagues of their lost loved ones. We’re keen to see change in the industry to ensure all of our people are safe and well. We’ve partnered with MATES to help achieve that change and to support our people to ask for help when they’re feeling low, as a regular part of life."
MATES is proud to be a part of the support team for the project looking after the alliance’s workers on site and in the project offices, too. We are stronger together.

