Construction





Work in progress 


Completion of a big project like the busway creates change and some disruption. We’re keen to be good neighbours while the work is in progress and to keep you updated so you know what to expect.


Check below for current and upcoming road layout changes and work in your area while the Eastern Busway is built.


Where
Activity
What’s happening
From
To
Pakūranga to Mattson Road

Reeves Road/ Aylesbury Street/ William Roberts Road intersection

day and night work 

Current stage includes road closures of William Roberts Road where it intersects with Reeves Road from 20 July to late September

- Two-way stop/go traffic on Reeves Road. 

Drainage upgrades and installation of fully signalised intersection

*Various closures are required to complete this work.

8 June

End of November

Tī Rākau Drive at the intersection of Tī Rākau Park/William Roberts Road

Day work

(occasional night work)

Stormwater and water main upgrades and pavements work. 

June

November

Tī Rākau Drive from Pakūranga Road to Mattson Road

Night work 

Planting in the medians and drainage areas along Tī Rākau Drive.

*This work requires lane closures. 

August 

Late September

Pakūranga Bus Station on Tī Rākau Drive in the bus lanes

Day work (occasional night work)

Construction of bus shelters in the bus lanes. Current work includes early morning concrete pours.

Current

Mid October

Pakūranga Road, from Rā Hihi - flyover to Tī Rākau Drive

Day and night work 

Investigation works for redundant storm water grouting 

24 August 

End of November

Brampton Court/ Pakūranga Road intersection

Day and night work 

Brampton Court signalisation - installing traffic lights, pram crossing and tactile pavers. 

Work commences on Monday 21 September, for two weeks to construct the new signalised intersection. Signals will be turned on in early November.

21 September

Early November

Pakūranga Highway/ Tī Rākau Drive intersection

Day and night work 

The intersection will be closed. Pakūranga Highway onramp and offramp will be open during the closure. Access to businesses along Tī Rākau Drive remain open.

24 October

25 October

Tī Rākau Drive/ Mattson Road intersection

Day and night work 

Temporary lane layout changes and detours will be in place at times

27 October 

29 October

Tī Rākau Drive / Pakūranga Road intersection 

Night and weekend work

Installation of raised speed table on the free left-hand turn to Pakūranga Road 

20 September

4 October

Mattson Road to Tī Rākau bridge

Tī Rākau Drive (between Roseburn Place and Gossamer Drive)

Night work 

Installing plants, kerbs, streetlights and traffic pole connections within the medians along Tī Rākau Drive at night. 

27 September

2 October

Tī Rākau Drive (between 160 and 174 Tī Rākau Drive)

Night work 

Final layer of asphalt being laid between 160 and 174 Ti Rakau Drive.

1 October

2 October

Tī Rākau Drive (residential eastbound lanes)

Night work 

On-street parking will be removed permanently following the installation of line marking.

4 October

Mid-October

Bus Stations (Koata - Riverhills & Te Taha Wai - Edgewater Stations)

Night work 

Removing scaffolding, connecting the power and underground services to the structures. One eastbound lane will be closed on Tī Rākau Drive when we are working. 

5 October

Mid-October

Gossamer Drive intersection

Night work 

Installing kerbs and median island

Early-October

Mid-October

Edgewater Drive (east) intersection

Night work 

Installing kerbs and median island 

Early-October

Mid-October

84 to 214 Tī Rākau Drive properties

Day and night work

Improving the local stormwater network and installing new footpaths, kerbs and road surfacing.


15 June 


early-October

Burswood, Huntington Park and Botany 

Burswood

day and night work 

Burswood Drive closed at eastern end (near Bunnings) to construct the new busway intersection.

September

5 October

Greenmount Drive

day and night work 

Right turn into and out of Greenmount Drive closed while work is completed for busway and intersectoin with Ti Rākau Drive

25 September 

10 October 

Tī Rākau Drive between Greenmount Drive and Huntington Drive

day and night work 

Labour Weekend - extensive programme of work happening over long weekend while there is less traffic on the road.

23 October

27 October

Huntington Drive

day and night work 

Right turn into and out of Greenmount Drive closed while work is completed for busway and intersection with Tī Rākau Drive.

Ongoing 

November 2026

Whakamaumahara

Guys Reserve

day and night work

Construction on final stage of Eastern Busway

March 2026 

Mid 2027

  • Timeline Alternate Text

    The project timeline is a summary of the main activities on the project between now and 2027. See at a glance what’s in progress and what’s coming up in the next few years.



    Construction timeline

  • Facts to know during construction Alternate Text

  • Supporting MATES in Construction Alternate Text

    The alliance is delighted to become a Premium Plus sponsor of MATES in Construction, an organisation helping to reduce the lives lost to suicide in the construction industry.


    Alliance project director Matt Zame says that the five organisations of the alliance have been affected by suicide and the ripples it causes.  "Suicide has a profound and lasting impact on the families, friends and colleagues of their lost loved ones. We’re keen to see change in the industry to ensure all of our people are safe and well. We’ve partnered with MATES to help achieve that change and to support our people to ask for help when they’re feeling low, as a regular part of life."


    MATES is proud to be a part of the support team for the project looking after the alliance’s workers on site and in the project offices, too. We are stronger together.