Construction





Work in progress 


Completion of a big project like the busway creates change and some disruption. We’re keen to be good neighbours while the work is in progress and to keep you updated so you know what to expect.


Check below for current and upcoming road layout changes and work in your area while the Eastern Busway is built.


Where
Activity
What’s happening
From
To
Pakūranga to Mattson Road

Reeves Road/ Aylesbury Street/ William Roberts Road intersection

day and night work 

Final stage includes road closures of Reeves Road between William Roberts Road and Aylesbury Street - 18 October to End of November 

- Stop/go traffic between Reeves Road and William Roberts Road.

- Two-way traffic between Aylesbury Street and Reeves Road (under Rā Hihi-flyover) 


Drainage completed. Work underway to build road and intersections including installation of traffic light signals


2 and 3 November - pavements work at night 

8 June

Late November

Brampton Court and Pakūranga Road intersection

Night work 

Utilities installation

1 November - traffic lights will become live

15 October 

1 November 

Pakūranga Road, from Rā Hihi - flyover to Tī Rākau Drive

Day and night work 

Grouting the redundant storm water line along Pakūranga Road and installing cycleway separators

27 October 

Late November

Tī Rākau Drive from Mattson Road to Pakūranga Highway onramp

Night work 

Final stormwater network work

18 October 

19 November

Bolina Crescent 

Day work 

Stormwater drainage work

Early October

Early November

Pakūranga Town Centre

Day and night work 

Ongoing minor works including traffic signs around Pakūranga Town Centre

Late October

Early December

Tī Rākau Drive and William Roberts Road intersection 

Night work 

Construct median island and install traffic signals 

10 to 12 November - final surfacing work 

1 November

Mid-November

Mattson Road to Tī Rākau bridge

Tī Rākau Drive intersections (Edgewater Drive east, Roseburn U-turn, Gossamer Drive)

Night work 

24/7 work along Tī Rākau Drive from Friday 30 October to Sunday 1 November (weather dependent)


Grouting redundant stormwater pipes, testing new streetlights, completing the intersection and median kerbs and laying asphalt

28 October

3 November 

Gossamer Drive intersection

Night work 

Installing kerbs and median island and final surfacing 

Late-October

Mid-November

Edgewater Drive (east) intersection

Night work 

Installing kerbs and median island and final surfacing 

Early-October

Mid-November

Burswood, Huntington Park and Botany 

Huntington Drive

day and night work 

Right turn into and out of Greenmount Drive closed while work is completed for busway and intersection with Tī Rākau Drive.

Ongoing 

November 2026

Whakamaumahara

Guys Reserve

day and night work

Construction on final stage of Eastern Busway

March 2026 

Mid 2027

  • Timeline Alternate Text

    The project timeline is a summary of the main activities on the project between now and 2027. See at a glance what’s in progress and what’s coming up in the next few years.



    Construction timeline

  • Facts to know during construction Alternate Text

  • Supporting MATES in Construction Alternate Text

    The alliance is delighted to become a Premium Plus sponsor of MATES in Construction, an organisation helping to reduce the lives lost to suicide in the construction industry.


    Alliance project director Matt Zame says that the five organisations of the alliance have been affected by suicide and the ripples it causes.  "Suicide has a profound and lasting impact on the families, friends and colleagues of their lost loved ones. We’re keen to see change in the industry to ensure all of our people are safe and well. We’ve partnered with MATES to help achieve that change and to support our people to ask for help when they’re feeling low, as a regular part of life."


    MATES is proud to be a part of the support team for the project looking after the alliance’s workers on site and in the project offices, too. We are stronger together.